Building Services 5 Year Plan

The following is a school-by-school priority listing of projects slated for completion if referendum Question #1 is approved by the voters. The list, compiled by the district's Building Services staff, is based on current needs and is subject to change if an emergency occurs. In that case, resources would be diverted to ensure the health and safety of students and staff.

The "Total Score" column refers to the priority of the building project. The District has developed a system that scores a project by such things as needs, useful life and condition. A higher score indicates a more urgent need to complete the project. To see what each project may encompass, see the Project Descriptions.

The estimate for each project may include any of the following; asbestos abatement, lead paint abatement, control work, miscellaneous trade work, design cost, profit, and overhead. An example would be a boiler replacement. This project may involve design to determine optimum boiler size, control work to base load one boiler, removal of asbestos insulation on the old boiler, pouring a new concrete pad, steam piping and insulation, ductwork and replacement of the flue. Thus, each project varies slighting depending on the particular conditions of each building.

BUILDING TOTAL SCORE YEAR YEAR-Revised PROJECT SCOPE COST ESTIMATE ACTUAL COST CONTRACTOR STATUS
ADMIN 21   1 Clean Ductwork $60,000.00 $40,000.00 Various Complete
ALLIS 26 2 1 Exterior fire escape $0.00 $14,117.00 Joe Daniels Complete
EAST 24 5 1 Repair broken sidewalks $10,000.00 $5,000.00   Part of 5th Street project waiting on bill from City
EAST 23 1 1 Roof replacement - partial $206,377.00 $233,570.00 Gary Brown Roofing Complete
EMERSON 28 1 1 LMC flooring $10,000.00 $22,376.00 Sergenians Complete
FRANKLIN 23 5 1 PA/intercom/phone $45,000.00 $31,981.00 Ameritech Complete
HAMILTON/ VANHISE 20 1 1 Roof replacement - partial $129,900.00 $277,325.00 Gary Brown Roofing Complete
LaFOLLETTE 31 1 1 Roof replacement - partial $210,000.00 $233,570.00 Gary Brown Roofing Complete
LINCOLN 32 1 1 Emergency lighting battery packs $9,000.00 $6,467.00 Forward Complete
MEMORIAL 28 1 1 Chiller and Cooling Towers $70,500.00 $70,274.00 Trane, Honeywell Cooling tower complete
MEMORIAL 9   1 PA - Auditorium $21,000.00 $31,458.00 Full Compass Complete
MEMORIAL 25 1 1 Roof replacement - partial $286,500.00 $198,751.00 Southern WI Roofing Complete, included Mansfield roof
MIDVALE 21 5 1 Sewer lateral replacement $15,000.00 $8,000.00 Pertzborn Complete
O'KEEFFE/ MARQUETTE 13   1 Replace Entrance Doors $24,600.00 $7,500.00 In-House Complete
RANDALL 26 1 1 Plumbing upgrades $200,000.00 $130,361.00 H&H Plumbing Complete
SHERMAN 29 1 1 Roof replacement - partial, tuckpointing, brick repair $156,200.00 $128,664.00 Maly Roofing contract goes to BOE 2/12/01, Tuckpointing complete.
SHERMAN 19   1 Wall on N. end of Sherman $10,000.00 District Wide Tuckpointing Shower Complete
SPRING HAR. 31 1 1 Emergency lighting battery packs $5,500.00 $5,304.00 Forward Complete
TOKI/ OR.RDG 24 1 1 Replace replacement - partial $100,000.00 $141,613.00 S.H. Christiansen Complete
VARIOUS 15   1 Water softeners, Water heaters, Admin, Allis, Blackhawk, Crestwood, Elvehjem, Emerson, Glendale, Hoyt, Jefferson, Kennedy, Lindbergh, Lowell, Mansfield, Memorial, Mendota, Sherman, Whitehorse $18,720.00 $18,720.00 Hellendbrand Complete, lease/purchase for 5 yrs
WEST 25 1 1 Roof replacement - partial $192,520.00 $218,018.00 Tilsen Complete
WTHORSE/ SCHENK 47 1 1 Electrical Upgrade, ceilings, lighting, fire alarm $582,700.00 $450,000.00 Forward Lighting goes to BOE 2/12/01
WTHORSE/ SCHENK 32 1 1 Replace rooftop unit $73,500.00 $112,426.00 Trane, Commercial Air Complete
WTHORSE/ SCHENK 24 1 1 Unit Ventilators $151,200.00 $282,420.00 Trane, Commercial Air Complete
YEAR 1 TOTALS         $2,588,217.00 $2,667,915.00    
BUILDING TOTAL SCORE YEAR YEAR-Revised PROJECT SCOPE COST ESTIMATE FAC. AUD. ITEMS ACTUAL COST CONTRACTOR STATUS
  31 3 2 Temp controls   $52,660.00 Honeywell Performance Contract PHII, to BOE 2/12/01
BLACKHAWK/ GOMPERS 24 3 2 Electrical Upgrade $264,700.00      
BLACKHAWK/ GOMPERS 35 5 2 fire alarm, security and gym PA system $200,000.00      
CHEROKEE 23 2 2 Roof replacement - partial $195,400.00     In Design
CHEROKEE N/A 2 2 Rooftop unit $115,000.00     In Design
CRESTWOOD 32 4 2 Temperature controls $214,500.00 $89,630.00 Honeywell Performance Contract PHII, to BOE 2/12/01
EAST 30 2 2 Chiller R-12 $60,000.00     In Design, Lease/Purchase for 5 yrs
FRANKLIN 24   2 Temperature controls $194,700.00 $49,688.00 Honeywell Performance Contract PHII, to BOE 2/12/01
HAMILTON/ VANHISE 23 2 2 Roof replacement - partial $41,100.00     In Design
HAWTHORNE 25 4 2 Emergency lighting, mech.rm. lighting $10,200.00      
HAWTHORNE 22 5 2 Exterior doors $19,200.00     Part of Addition, bids due 2/8/01
HAWTHORNE 26 5 2 Exterior lighting $2,200.00     Part of Addition, bids due 2/8/01
HAWTHORNE 32 3 2 Fire alarm system $79,416.00      
HAWTHORNE 23 5 2 Temperature controls $118,800.00 $52,710.00 Honeywell Part of Addition, bids due 2/8/01
HOYT 33 2 2 Fire alarm upgrade $62,927.00     On street 2/22/01
JEFFERSON 33 2 2 Fire alarm $110,000.00     Bids due 2/22/01
JEFFERSON 32 2 2 Generator & automatic transfer switch $45,000.00     Bids due 2/22/01
LaFOLLETTE 21 5 2 Corridor floors $155,000.00 $20,000.00   In-house, summer 2001
LaFOLLETTE 26 2 2 Roof replacement - partial $86,000.00     In Design
LEOPOLD 24 2 2 Roof replacement - partial $180,000.00     In Design
LINDBERGH 24 2 2 Roof replacement - partial $110,500.00     In Design
MEMORIAL 28 1 2 Chiller $45,000.00     In Design, Lease/Purchase for 5 yrs
MEMORIAL 24 2 2 Roof replacement - partial $100,700.00     In Design
MUIR 32 3 2 Temperature controls $215,600.00 $30,000.00 Honeywell Performance Contract PHII, to BOE 2/12/01
RANDALL 33 2 2 Air handling unit replacement $165,000.00     In Design
RANDALL 28 2 2 Lighting - Gym $11,000.00     In-house, summer 2001
RANDALL 32 2 2 Temperature controls $211,000.00 $66,495.00 Honeywell Performance Contract PHII, to BOE 2/12/01
SHERMAN 22 5 2 Branch wiring, devices $159,000.00      
SHERMAN 25 5 2 Exterior windows $400,000.00      
SHERMAN 26 5 2 Indoor air quality - office area $25,100.00      
SHOREWOOD 32 3 2 Temperature controls $220,000.00 $97,783.00 Honeywell Performance Contract PHII, to BOE 2/12/01
SPRING HAR. 14   2 Exterior tile $35,000.00   In-House In design
SPRING HAR. 14   2 PBX Phone system $45,000.00 $0.00    
STEPHENS 32 2 2 Temperature controls $234,200.00 $77,733.00 Honeywell Performance Contract PHII, to BOE 2/12/01
THOREAU 32 2 2 Rooftop air handling units, temperature controls $431,200.00 $503,730.00 Honeywell Performance Contract PHII, to BOE 2/12/01
THOREAU 31 2 2 Rooftop units, gym and classrm $88,000.00 $0.00 Honeywell Performance Contract PHII, to BOE 2/12/01
VARIOUS 15   2 Water softeners, Water heaters, Admin, Allis, Blackhawk, Crestwood, Elvehjem, Emerson, Glendale, Hoyt, Jefferson, Kennedy, Lindbergh, Lowell, Mansfield, Memorial, Mendota, Sherman, Whitehorse $18,720.00 $18,720.00 Hellendbrand Complete, lease/purchase for 5 yrs
WEST 21 2 2 Roof replacement - partial $72,500.00     In Design
YEAR 2 TOTALS         $4,902,363.00 $3,699,092.00 $3,589,000 Temp control reduced estimate - $1,052,80, LAF floors - in-house $135,000
BUILDING TOTAL SCORE YEAR YEAR-Revised PROJECT SCOPE COST ESTIMATE FAC. AUD. ITEMS ACTUAL COST CONTRACTOR STATUS
  23 3 3 Roof replacement - partial        
CRESTWOOD 23 3 3 Roof, center $50,000.00      
EAST 30 2 3 Chiller R-12 $60,000.00     In Design, Lease/Purchase for 5 yrs
EAST 12   3 Telecommunications $275,000.00     TEACH
ELVEHJEM 22 3 3 Roof - original $300,000.00      
HAMILTON/ VANHISE 22 5 3 Electrical distribution switchboard, panelbds $223,700.00     TEACH
JEFFERSON 29 3 3 Air handling unit modifications for indoor air quality concerns and controls $50,000.00      
LAKEVIEW 33 3 3 Electrical, lighting upgrade, ceilings $297,300.00      
LAKEVIEW 26 3 3 Em. lighting battery packs $10,000.00      
LAKEVIEW 23 3 3 Exterior lighting $7,000.00      
LAKEVIEW 32 2 3 Fire alarm system $75,178.00     Postponed
LAKEVIEW 22 3 3 PA system $45,000.00      
LAPHAM 33 2 3 Electrical, lighting upgrade, ceilings, floors, including ACM removal, 3rd floor $554,933.00     Postponed
LINDBERGH 32 3 3 Fire alarm system $63,944.00      
LOWELL 22 3 3 Window lintels $10,000.00      
MEMORIAL 28 1 3 Chiller $45,000.00     In Design, Lease/Purchase for 5 yrs
MEMORIAL 24 4 3 Electrical main distribution panel#3, panelbds, feeders $46,300.00     TEACH
MEMORIAL 23 4 3 Electrical main distribution panel#4 starters $7,400.00     TEACH
MEMORIAL 12   3 Telecommunications $275,000.00     TEACH
MIDVALE 12   3 Telecommunications replacement $45,000.00     TEACH
MUIR 30 3 3 Lighting upgrade, ceilings $300,000.00      
SANDBURG 23 3 3 Roof - Entire $230,000.00      
SHOREWOOD 29 3 3 Electrical and lighting upgrade $494,200.00      
SHOREWOOD 22 3 3 Misc. pumps $5,000.00      
SHOREWOOD 23 3 3 Roof replacement - partial $152,800.00      
SHOREWOOD 24 3 3 Telecommunications replacement $45,000.00      
SPRING HAR. 25 5 3 Electrical upgrade $93,500.00      
THOREAU 25 2 3 Roof replacement - partial $105,000.00     In Design
VARIOUS 15   3 Water softeners, Water heaters, Admin, Allis, Blackhawk, Crestwood, Elvehjem, Emerson, Glendale, Hoyt, Jefferson, Kennedy, Lindbergh, Lowell, Mansfield, Memorial, Mendota, Sherman, Whitehorse $18,720.00 $18,720.00 Hellendbrand Complete, lease/purchase for 5 yrs
YEAR 3 TOTALS         $4,262,575.00   $4,147,000  
BUILDING TOTAL SCORE YEAR YEAR-Revised PROJECT SCOPE COST ESTIMATE FAC. AUD. ITEMS ACTUAL COST CONTRACTOR STATUS
  22 3 4 Stone column cladding        
ALLIS 29 3 4 Unit ventilatiors $93,500.00      
ALLIS 30 5 4 Boilers $38,900.00      
ALLIS 24 5 4 Roof replacement - partial $40,000.00      
ALLIS 34 5 4 Lighting upgrades $50,000.00      
CHEROKEE 30 4 4 Fire alarm system $71,500.00      
CHEROKEE 30 4 4 Lighting upgrades $194,000.00      
CHEROKEE 22 4 4 Window replacement $180,000.00      
CRESTWOOD 31 4 4 Electrical and lighting upgrade, Ceilings $365,000.00      
CRESTWOOD 29 4 4 Exterior windows $36,800.00      
EAST 30 2 4 Chiller R-12 $60,000.00     In Design, Lease/Purchase for 5 yrs
EAST 21 4 4 Pool exhaust fans $6,600.00      
EAST 23 5 4 Plaza, entry, parking lot lighting $11,500.00      
EAST 23 5 4 Replace flooring IMC $15,400.00      
FRANKLIN 24 5 4 Fire alarm system $96,525.00      
JEFFERSON 23 4 4 Patch concrete curb, replace planter box $15,000.00      
LaFOLLETTE 12   4 Telecommunications $275,000.00     TEACH
LAKEVIEW 28 3 4 Unit ventilators $105,600.00      
LAPHAM 30 4 4 Air handling units, gym uv's $31,900.00      
LAPHAM 33 3 4 Electrical, lighting upgrade, ceilings, floors, including ACM removal, 2nd floor $554,933.00      
LAPHAM 30 4 4 Unit ventilators $16,000.00      
LINCOLN 30 4 4 Lighting upgrade and ceiling replacement, classrooms, offices $80,000.00      
LOWELL 29 4 4 Air handling unit - north side $66,500.00      
LOWELL 23 4 4 Exterior lighting $5,000.00      
LOWELL 22 4 4 Heating system hot deck coils $8,300.00      
LOWELL 25 4 4 Paint/plaster walls $51,400.00      
LOWELL 23 4 4 Steam and control valves $104,500.00      
LOWELL 31 4 4 Electrical and lighting upgrade, replace ceilings $590,000.00      
MEMORIAL 28 1 4 Chiller $45,000.00     In Design, Lease/Purchase for 5 yrs
MEMORIAL 25 4 4 Water coolers $27,900.00      
MENDOTA 29 4 4 Replace exterior windows $183,800.00      
MENDOTA 30 4 4 Replace unit ventilators $83,600.00      
MUIR 31 4 4 Furnace $600,000.00      
SHERMAN 23 3 4 Landing, Drainage, Resurface north side of drive $24,000.00      
SPRING HAR. 25 4 4 Window pane replacement $50,000.00      
TOKI/ OR.RDG 23 4 4 Roof - Elementary side $63,200.00      
VARIOUS 15   4 Water softeners, Water heaters, Admin, Allis, Blackhawk, Crestwood, Elvehjem, Emerson, Glendale, Hoyt, Jefferson, Kennedy, Lindbergh, Lowell, Mansfield, Memorial, Mendota, Sherman, Whitehorse $18,720.00 $18,720.00 Hellendbrand Complete, lease/purchase for 5 yrs
WEST 23 4 4 Replace Fire Alarm System $455,000.00      
YEAR 4 TOTALS         $4,718,078.00   $4,737,000  
BUILDING TOTAL SCORE YEAR YEAR-Revised PROJECT SCOPE COST ESTIMATE FAC. AUD. ITEMS ACTUAL COST CONTRACTOR STATUS
  21 5 5 Site drainage        
EAST 30 2 5 Chiller R-12 $60,000.00     In Design, Lease/Purchase for 5 yrs
EAST 24 5 5 Fume hoods, lab $120,000.00      
ELVEHJEM 24 5 5 Water coolers $3,400.00      
EMERSON 24 5 5 Lighting upgrades $233,200.00      
EMERSON 22 5 5 Resurface playground $75,000.00      
EMERSON 26 5 5 Roof replacement - partial $25,000.00      
EMERSON 24 5 5 Water coolers $4,000.00      
FRANKLIN 26 5 5 Sink Replacement $25,000.00      
FRANKLIN 28 5 5 Unit ventilators $132,000.00      
GLENDALE 26 5 5 Exterior lighting $6,000.00      
GLENDALE 26 5 5 Sink Replacement $41,600.00      
GLENDALE 26 5 5 Unit ventilator, office $8,000.00      
HAMILTON/ VANHISE 29 5 5 Ceiling, lighting, gym $38,300.00      
HAMILTON/ VANHISE 25 5 5 Replace Unit Ventilators $224,000.00      
HOYT 28 5 5 Unit ventilators $14,300.00      
HUEGEL 27 5 5 Exterior lighting $15,000.00      
HUEGEL 22 5 5 Flooring, 127,126,125,124 $10,000.00      
JEFFERSON 21 5 5 Lighting, bldg. Mtd. $21,000.00      
JEFFERSON 23 5 5 Underground fuel oil storage tank replacement $25,000.00      
KENNEDY 26 5 5 Flooring, corridors, gym, LMC $49,500.00      
KENNEDY 23 5 5 Lighting, walkway, parking $12,000.00      
KENNEDY 22 5 5 Roof, entire $120,000.00      
LaFOLLETTE 23 5 5 Repave courtyard, entry walk, replace concrete landing to lower level $33,900.00      
LaFOLLETTE 28 5 5 Water coolers $53,900.00      
LAPHAM 33 4 5 Electrical, lighting upgrade, ceilings, floors, including ACM removal, 1st floor $554,933.00      
LINDBERGH 22 5 5 Exterior lighting $9,000.00      
LINDBERGH 28 5 5 Furnace replacement $600,000.00      
LINDBERGH 29 5 5 Lighting upgrades, ceiling replacement $127,500.00      
MEMORIAL 28 1 5 Chiller $45,000.00     In Design, Lease/Purchase for 5 yrs
MIDVALE 32 5 5 Electrical, lighting Upgrade, ceilings $478,700.00      
MIDVALE 26 5 5 Sink Replacement $50,000.00      
MIDVALE 30 5 5 Unit ventilators $118,000.00      
MUIR 23 5 5 Water coolers $3,000.00      
O'KEEFFE/ MARQUETTE 26 5 5 Plumbing fixtures $30,500.00      
SANDBURG 23 5 5 Exterior lighting $5,500.00      
SANDBURG 28 5 5 Unit ventilators $88,000.00      
SENNETT 22 5 5 Exterior doors and windows $81,500.00      
TOKI/ OR.RDG 22 5 5 Replace rooftop unit $92,600.00      
TOKI/ OR.RDG 25 5 5 Unit Ventilators $80,900.00      
VARIOUS 15   5 Water softeners, Water heaters, Admin, Allis, Blackhawk, Crestwood, Elvehjem, Emerson, Glendale, Hoyt, Jefferson, Kennedy, Lindbergh, Lowell, Mansfield, Memorial, Mendota, Sherman, Whitehorse $18,720.00 $18,720.00 Hellendbrand Complete, lease/purchase for 5 yrs
WTHORSE/ SCHENK 26 4 5 Repair stucco finish below windows, replace doors and windows $576,300.00      
FALK 29   5 Lighting upgrade $80,700.00      
HUEGEL 29   5 Lighting upgrade $74,400.00      
ADMIN 28   5 Fire alarm, ceiling $156,296.00      
ALLIS 28   5 Replace concrete steps, Retaining Wall $40,000.00      
ADMIN 25   5 Emergency generator $45,000.00      
EAST 22   5 Casework in labs $49,000.00      
RANDALL 22   5 Master clock & bell, telephone, PA $45,000.00      
ALLIS 21   5 Flooring - LMC $8,500.00      
CHEROKEE 21   5 Replace dust collector $13,200.00      
EAST 21   5 Toilet partitions, Boys room $10,500.00      
YEAR 5 TOTALS         $4,841,349.00   $4,863,000  
BUILDING TOTAL SCORE YEAR YEAR-Revised PROJECT SCOPE COST ESTIMATE FAC. AUD. ITEMS ACTUAL COST CONTRACTOR STATUS
  21     Roof fans        
HAWTHORNE 21     Roof fans $7,200.00      
MEMORIAL 21     Dust collectors $10,300.00      
MENDOTA 21     Roof exhaust fans $9,400.00      
MENDOTA 21     Roof replacement - partial $40,000.00      
WEST 21     Lighting, pnlbds boiler room $45,100.00      
BLACKHAWK/ GOMPERS 20     Window replacement $91,900.00      
EAST 20     Exhaust fans, penthouse $4,000.00      
HAWTHORNE 20     Exterior windows, curtainwall $340,200.00      
LaFOLLETTE 20     Bleachers gym, pool $155,000.00      
LaFOLLETTE 20     Electrical upgrade, main distribution panel#1, subpanels, wire and devices. $503,900.00      
LaFOLLETTE 20     Motor starters $41,800.00      
SHERMAN 20     Storm collection systems $18,700.00      
SPRING HAR. 20     Door replacement $25,000.00      
THOREAU 20     Lighting upgrade, replace ceilings $159,300.00      
WTHORSE/ SCHENK 20     Replace Dust Collector $5,500.00      
EAST 19     Bleachers $100,000.00      
EMERSON 19     Gymnasium ceiling $4,800.00      
LAPHAM 19     Exterior doors and glazed windows $28,200.00      
LINCOLN 19     PA, master clock system $17,600.00      
MIDVALE 19     Chimney repairs $10,000.00      
MIDVALE 19     Exterior windows $128,600.00      
MIDVALE 19     Generator $45,000.00      
SANDBURG 19     Electrical branch devices(outlets, switches, starters) $28,600.00      
SHERMAN 19     Elevator $150,000.00      
TOKI/ OR.RDG 19     Parking lot, playground paving, playground drainage, remove old entrance $300,000.00      
BLACKHAWK/ GOMPERS 18     Exterior Lighting $11,000.00      
EMERSON 18     Brickwork at 1/2 landing $5,000.00      
EMERSON 18     Concrete steps $45,000.00      
EMERSON 18     Steam heating system feed water pumps, tank, condensate pumps $14,000.00      
GLENDALE 18     Stone sill replacement $2,500.00      
HAMILTON/ VANHISE 18     Concrete walk, steps, retaining walls, sealants $25,000.00      
HAMILTON/ VANHISE 18     Water coolers $4,700.00      
JEFFERSON 18     Water coolers $6,900.00      
KENNEDY 18     Ceilings, corridors, gym $20,700.00      
LAPHAM 18     Parking lot paved surface $125,000.00      
LOWELL 18     Emergency lighting $21,400.00      
MEMORIAL 18     Exterior lighting $27,000.00      
MIDVALE 18     Asphalt - kindergarten entrance $20,000.00      
RANDALL 18     Flooring, corridors, LMC $35,600.00      
ADMIN 17     Structural repair - boiler room $12,600.00      
EAST 17     Eye wash stations $18,000.00      
EAST 17     Safety showers $9,000.00      
KENNEDY 17     Wash fountain $29,700.00      
THOREAU 17     Tuckpointing $5,000.00      
WEST 17     Exterior doors $84,000.00      
ADMIN 16     Chillers $206,800.00      
BLACKHAWK/ GOMPERS 16     Eye wash $600.00      
EAST 16     Cooling tower and supports $120,000.00      
ELVEHJEM 16     Steam heating system chemical feedwater tank $5,000.00      
JEFFERSON 16     Hot water supply compression tanks $3,300.00      
LOWELL 16     Ceiling auditorium, toilets, lighting $15,000.00      
SHERMAN 16     Plumbing Fixtures $58,300.00      
SHERMAN 16     Renovate theater $250,000.00      
SHOREWOOD 16     Sanitary backflow protection $37,800.00      
TOKI/ OR.RDG 16     Fire alarm system $150,000.00      
TOKI/ OR.RDG 16     Replace dust collector $8,300.00      
TOKI/ OR.RDG 16     Replace water coolers $9,500.00      
WEST 16     Main entrance steps $10,000.00      
BLACKHAWK/ GOMPERS 15     Locker room showers $23,100.00      
FRANKLIN 15     Interior door, hardware $110,000.00      
JEFFERSON 15     Wash fountains $41,800.00      
LAKEVIEW 15     Playground paved surface $30,000.00      
LAPHAM 15     Parapet wall, tuckpointing $32,500.00      
LEOPOLD 15     Concrete walk repairs $3,200.00      
LINCOLN 15     Replace Steam Traps $1,500.00      
LOWELL 15     Exterior doors $3,500.00      
MANSFIELD 15     Replace wood benches $1,200.00      
MENDOTA 15     Condensate Pumps and Steam Traps $6,000.00      
MIDVALE 15     Interior doors and hardware $150,000.00      
MUIR 15     Flooring in old building corridors $25,000.00      
MUIR 15     Replace water heaters $7,500.00      
O'KEEFFE/ MARQUETTE 15     Wash fountain $15,800.00      
SENNETT 15     Site repairs $5,000.00      
STEPHENS 15     Corridor HW Converter $5,000.00      
STEPHENS 15     Feedwater & Condensate Pumps $8,500.00      
STEPHENS 15     Replace Steam traps $3,500.00      
TOKI/ OR.RDG 15     Lighting fixtures - Bldg Mtd. $4,000.00      
TOKI/ OR.RDG 15     Replace curtainwall system $472,500.00      
WEST 15     Security system $60,500.00      
ADMIN 14     Plaster repair $5,000.00      
ALLIS 14     Ceiling, lighting cafeteria $15,300.00      
ALLIS 14     Steam valves, steam convectors, control valves $58,900.00      
BLACKHAWK/ GOMPERS 14     Replace Condensate and Feedwater Pumps $24,200.00      
CHEROKEE 14     Replace chimney $3,000.00      
CRESTWOOD 14     Steam heating system chemical feedwater tank $5,500.00      
FALK 14     Steam heating chemical feedwater tank $5,000.00      
FRANKLIN 14     Flooring, LMC, corridors $15,800.00      
FRANKLIN 14     Steam heating system feed water tank $15,000.00      
GLENDALE 14     Misc. pumps $1,200.00      
GLENDALE 14     Parking lot surface $80,000.00      
GLENDALE 14     Playground surface $150,000.00      
GLENDALE 14     Steam heating system feedwater tank $15,000.00      
HAMILTON/ VANHISE 14     Replace Condensate Pumps $21,000.00      
HAWTHORNE 14     Parking lot surface $120,000.00      
HUEGEL 14     PA system - gym $5,300.00      
LaFOLLETTE 14     Athletic lockers $10,000.00      
LaFOLLETTE 14     Condensate Pumps $14,000.00      
LAPHAM 14     Interior doors $165,000.00      
LEOPOLD 14     ADA Elevator $120,000.00      
LINCOLN 14     Parking lot paved surface $60,000.00      
LOWELL 14     Cafeteria wall $26,300.00      
LOWELL 14     Casework $2,500.00      
LOWELL 14     Interior doors $200,000.00      
LOWELL 14     Steam heating system chemical feed tanks $5,000.00      
MUIR 14     Misc. pumps $2,000.00      
O'KEEFFE/ MARQUETTE 14     Replace Condensate Pumps $10,000.00      
RANDALL 14     Steam heating system chemical feed water tank, traps $20,000.00      
SANDBURG 14     Replace Parking Lot $80,000.00      
SANDBURG 14     Steam heating system chemical feedwater tanks $15,000.00      
SENNETT 14     Resurface parking lot $160,000.00      
SHERMAN 14     Replace Condensate Pumps $17,000.00      
SHOREWOOD 14     Exterior doors $214,000.00      
SHOREWOOD 14     Steam heating system chemical feedwater tanks, traps $20,000.00      
SHOREWOOD 14     Steam hot water tank heaters $30,000.00      
STEPHENS 14     Steam heating system chemical feedwater tank $15,000.00      
WEST 14     Replace Condensate Pumps $56,000.00      
ADMIN 13     Exterior windows $128,600.00      
ALLIS 13     Steam heating system feedwater and condensate pumps $20,000.00      
GLENDALE 13     Flooring - toilets $18,000.00      
GLENDALE 13     Steam control valves $35,200.00      
HOYT 13     Exterior window hardware $25,000.00      
HUEGEL 13     Drainage at gym and flagpole $5,000.00      
KENNEDY 13     Steam heating control valves, traps $41,400.00      
KENNEDY 13     Thermostats $9,500.00      
LAKEVIEW 13     Flooring - gym $25,000.00      
LAPHAM 13     Pool plumbing $30,000.00      
LINCOLN 13     Exterior windows $73,500.00      
LINDBERGH 13     Water coolers $3,700.00      
MENDOTA 13     Air conditioning units, PTAC $3,300.00      
SANDBURG 13     Floor - LMC $8,600.00      
SHERMAN 13     Interior doors $148,000.00      
SHOREWOOD 13     Playground paved surface $12,000.00      
TOKI/ OR.RDG 13     Ductwork, stage & Office $18,700.00      
ADMIN 12     Steam heating system condensing units $29,700.00      
EAST 12     HWS and HWR steam valves(pre-1960) $139,700.00      
EAST 12     Moveable shelving, Rm 344, 38 $5,000.00      
EAST 12     Replace ceilings $200,000.00      
HUEGEL 12     Security gates, LMC $24,000.00      
HUEGEL 12     Security system $30,000.00      
LaFOLLETTE 12     Ceiling Replacement $100,000.00      
LAPHAM 12     Boilers $105,600.00      
LEOPOLD 12     Caulking at base $5,000.00      
LINDBERGH 12     Upgrade playground bridge $2,500.00      
MEMORIAL 12     Corridor ceilings $100,000.00      
MUIR 12     Vertical drop - playground area $2,000.00      
WEST 12     Ceiling. LMC $40,000.00      
WEST 12     Electrical service entrance switchboard, Main panel#4,5,6,7 $356,400.00      
WEST 12     Replace walk-in cooler $20,000.00      
WEST 12     Varsity tennis courts $240,000.00      
ADMIN 11     Boiler $91,600.00      
FALK 11     Steam heating control valves, traps $20,000.00      
HUEGEL 11     Parking surface $60,000.00      
HUEGEL 11     Playground surface $30,000.00      
LINDBERGH 11     Exhaust fans - roof prvs $17,600.00      
MANSFIELD 11     Shower mixing valves $1,000.00      
BLACKHAWK/ GOMPERS 10     Moveable partitions $5,000.00      
MANSFIELD 10     PA, lighting $116,000.00      
MANSFIELD 10     Regrade baseball field $50,000.00      
WTHORSE/ SCHENK 10     Replace cracked concrete flags $4,500.00      
BLACKHAWK/ GOMPERS 9     Interior ceramic base $5,000.00      
JEFFERSON 9     Replace Classroom Partitions $60,000.00      
MANSFIELD 9     Replace ceiling in locker and shower $75,000.00      
MIDVALE 9     Walks, retaining wall, concrete flags $13,700.00      
MUIR 9     Electrical Upgrade $250,000.00      
TOKI/ OR.RDG 9     Repair Mullions $1,500.00      
WEST 9     Stone retaining wall $60,000.00      
GLENDALE 8     Fencing $25,000.00      
LAKEVIEW 8     Drainage near entry $2,500.00      
FRANKLIN 7     Retaining wall and brick repairs $5,000.00      
LINCOLN 7     Brick repairs, tuckpointing $8,000.00      

Madison Schools Referendum - November 9, 1999