Complete Remediation
- Investigate and resolve all conditions in all parts of the building that are consistent with circumstances that may have contributed to mold growth in another part of the building.
- Investigate and resolve all conditions identified in the causation report.
Resolve Masonry Issues
- Fully inspect and evaluate conditions that may exist that could contribute to the building's ability to remain dry.
- Continue during next two weeks.
- Determine impact if any on reconstruction of interior spaces.
Legal Issues
- Continue to take necessary legal steps to preserve the fiduciary position of the school district.
Reconstruction Schedule
- Begin first week of May.
- Project can be completed in as short a timeline as 8 weeks.
- Length of timeline may be impacted by masonry work; stretching timeline to 13 weeks (without working overtime).
- Completion goal - first week of August.