From: Rick Hopke, Coordinator of Facility
Engineering
To: Roger Price, Assistant Superintendent Business
Services
Subject: Chávez Elementary School Reconstruction -
Progress Report Through 6/20/02
Roger,
Bachmann Construction Company, Inc. (BCCI) has completed the majority of the reconstruction on the first floor. Remaining work is pending receipt of materials and includes miscellaneous locker parts, rubber wall base and cabinets.
Custodial crews have begun cleaning rooms on the first floor.
BCCI has completed sealing interior masonry control joints above the ceilings per original construction documents.
Work continues on the second floor reconstruction. Crews are painting walls, installing cabinets and completing repairs to ceilings. Lockers are being installed as walls are completed.
The duct insulation is being fastened to duct work and is being repaired as needed.
All return and exhaust ducts continue to be protected with filter media to prevent construction dust from entering the ventilation systems.
Onyx has begun removing the lower 2 inches of gypsum board in the office area, strings room, LMC and Physical Education Office. Reconstruction by BCCI is scheduled to follow removal work.
The sky lights were scheduled to be repaired this week, but recent rains has delayed this work until early next week.
The cooling coil in Air Handling Unit #7 is being replaced.
Air balancing work is being scheduled to start in July.
BCCI has ordered the brick to used to make repairs to the exterior flashing. Delivery is expected in two weeks.
Work continues to be on schedule.
Rick Hopke
Coordinator of Facilities Engineering