Chávez Elementary School Reconstruction Status

From: Rick Hopke, Coordinator of Facility Engineering
To: Roger Price, Assistant Superintendent Business Services
Subject: Chávez Elementary School Reconstruction - Progress Report Through 7/11/02

Roger,

Bachmann Construction Company, Inc. (BCCI) has completed all the reconstruction on the first floor and the majority of work on the second floor.

Crews are completing the installation of data systems, paint touch-up and completing wall base installation.

Air balancing work is being scheduled for all areas to check for delivery of design air flows to all occupied spaces.

Filters on the second floor have been taken down as work in nearing completion.

Custodial crews continue to clean rooms on the first floor.

Work in the Office, LMC and storage areas has been completed.

Replacement of the existing kiln exhaust hood in the Art Room area has been completed.

A floor coating system has been select to seal the mechanical room floors. Work will be scheduled as soon as materials are received.

Brick to be used for exterior repairs is scheduled to be received this Friday. Masonry crews are scheduled to start work following receipt.

The roof edge modifications are scheduled to begin the week of July 15th.

Installation of the Closed Circuit TV system (CCTV) is scheduled to being the week of July 15th.

Work continues to be on schedule.

Rick Hopke
Coordinator of Facilities Engineering